Mumbai-Ahmedabad bullet train project may fail to meet 2023 deadline as COVID-19 pandemic causes delays

Apart from land acquisition and opening of tenders, a major cause for delay could be cost escalation owing to a fall in the rupee against the Japanese yen

Press Trust of India September 05, 2020 11:45:27 IST
Mumbai-Ahmedabad bullet train project may fail to meet 2023 deadline as COVID-19 pandemic causes delays

New Delhi: The Mumbai-Ahmedabad bullet train project, which is scheduled to be completed by December 2023, may fail to meet its deadline due to the coronavirus pandemic that has led to delays in opening tenders and land acquisition, officials said.

The National High Speed Rail Corporation (NHSRCL) has already acquired 63 percent of the land for the project - about 77 percent land in Gujarat, 80 percent in Dadra Nagar Haveli and 22 percent in Maharashtra. Officials said there are still issues in acquiring land in areas like Palghar in Maharashtra and Navsari in Gujarat.

Last year, the company had floated nine civil work tenders which could not be opened because of the coronavirus pandemic, officials said.

“Because of COVID we had to postpone the opening of a few of the tenders. It is difficult to assess the impact of the pandemic on the project as it is still continuing. We cannot say how the pandemic will affect the project as I don't know how long it will last,” NHSRCL MD Achal Khare said.

Officially, the NHSRCL spokesperson maintained that the deadline for the project remained 2023.

One of the civil work contracts for construction of stations, bridges, viaducts, maintenance depots, and tunnels across the network is to the tune of Rs 20,000 crore.

Tenders for civil works for 345 kms out of 508 kms alignment, or 68 percent of civil works, have already been floated. This includes six MAHSR stations (including one underground station in Mumbai). The works related to utility diversion are progressing well and the construction of Sabarmati passenger hub (a multi modal hub) in Sabarmati, Gujarat has also started.

The hostel building of High Speed Training Institute ( which is presently being used for COVID patients) and training tracks in Vadodara are also completed.

The 508.17-kilometre long network will pass through three districts in Maharashtra (Mumbai, Thane, and Palghar) and eight districts in Gujarat (Valsad, Navsari, Surat, Bharuch, Vadodara, Anand, Kheda, and Ahmedabad).

Apart from land acquisition, another major cause for delay could be cost escalation owing to a fall in the rupee against the Japanese yen.

The total cost of the project is pegged at Rs 1.08 lakh crore and as per the shareholding pattern, the Government of India is to pay Rs 10,000 crore to the NHSRCL, while the two states involved, Gujarat and Maharashtra, are to pay Rs 5,000 crore each. The rest is to be paid by Japan through a loan at 0.1 percent interest.

One section of the Ahmedabad-Mumbai high-speed rail corridor is likely to be tendered out within three months after nearly 90 percent of the land acquisition for the project is completed, an official said.

Updated Date:

also read

China reports its first monkeypox case in Chongqing city
World

China reports its first monkeypox case in Chongqing city

According to media reports, the monkeypox case was reported in a traveler who arrived in the city from overseas and is now receiving treatment at a designated hospital and is in stable condition

Coronavirus Update: India registers decrease in new Covid-19 cases
India

Coronavirus Update: India registers decrease in new Covid-19 cases

On Saturday, 5,747 new cases of coronavirus were registered in the country while 29 people died. A decrease of 83 has been registered in the daily number of newly infected Covid-19 patients as compared to yesterday

Global economy may suffer massive recession in 2023, warns World Bank
World

Global economy may suffer massive recession in 2023, warns World Bank

The World Bank report said that there are already many signs of a global slowdown. It said that the global economy is now poised for the sharpest recession since the 1970s