Maradu flats: SC says demolition must be completed in 138 days, directs Rs 25 lakh as interim compensation for owners

The Supreme Court on Friday directed that demolition of flats built on the coastal zone of Kochi's Maradu be completed in 138 days, in accordance with the time schedule provided by the Kerala government

Press Trust of India September 27, 2019 13:58:10 IST
Maradu flats: SC says demolition must be completed in 138 days, directs Rs 25 lakh as interim compensation for owners
  • The Supreme Court on Friday directed that demolition of flats built on the coastal zone of Kochi's Maradu be completed in 138 days, in accordance with the time schedule provided by the Kerala government

  • The apex court also directed payment of Rs 25 lakh as interim compensation by the state government to each flat owner within four weeks

  • The top court also ordered setting up of a one-member committee of retired high court judge to oversee demolition and assess total compensation

New Delhi: The Supreme Court on Friday directed that demolition of flats built on the coastal zone of Kochi's Maradu be completed in 138 days, in accordance with the time schedule provided by the Kerala government.

Maradu flats SC says demolition must be completed in 138 days directs Rs 25 lakh as interim compensation for owners

File image of the Supreme Court of India. PTI

The apex court also directed payment of Rs 25 lakh as interim compensation by the state government to each flat owner within four weeks. The top court also ordered setting up of a one-member committee of retired high court judge to oversee demolition and assess total compensation.

A bench comprising justices Arun Mishra and S Ravindra Bhat directed freezing of assets of builders and promoters who were involved in the construction of illegal buildings in the coastal zone areas of Kochi.

The bench further said the government may consider recovering the interim compensation amount from builders and promoters.

Kerala chief secretary Tom Jose was present at the hearing. The court said his presence would not be required during the next hearing on 25 October .

Senior advocate Harish Salve, appearing for the Kerala government, informed the bench that power and water supply were disconnected to the four apartment complexes in Kochi on Thursday.
The apex court said there should be no reason for delay in demolition and gave the example of Kant enclave in Faridabad where illegal structures have been demolished, and modalities of recovering the money from those responsible for such construction has been worked out.

The bench clarified that the court's primary concern was that no construction should have been carried out at the eco-fragile coastal zone and the question was not regarding any individual. While Salve was making submissions relating to the nitty gritty of demolition exercise that has to be carried out, the bench said, "If you cannot do it, we will think of involving some other outside agency."

Salve said the state government has submitted a plan under which in 138 days the structure would be demolished—including 90 days for demolition and 38 days for removing of debris. He said the buildings need to be brought down through implosion and expert agency will be appointed by 11 October to carry out the work.

The apex court on 23 September had said that illegal construction in coastal areas of Kerala is a "colossal loss" to the environment, and had expressed shock over spate of unauthorised structures coming up at Kochi's Maradu.

The top court had said that it appears that the authorities, rather than preventing the violations, were trying to mobilise the public opinion and time has come to hold them responsible for their active connivance in such activities of degrading the environment and violation of the coastal zone regulations. The apex court had also sought a concrete plan from the Kerala government on the removal of illegal structures.

On 8 May, the apex court had directed that these buildings be removed within a month as they were constructed in a notified CRZ, which was part of the tidally-influenced water body in Kerala. The court had passed the order after taking note of a report of a three-member committee, which said when the buildings were built, the area was already notified as a CRZ and construction was prohibited.

Earlier, the court had rejected a plea filed by the residents of the area against the demolition order and taken a strong exception to an order passed by a vacation bench during the summer break of the apex court, which had stayed the demolition of these buildings for six weeks.

Updated Date:

also read

Sourav Ganguly all set to continue as BCCI president for another term after SC accepts amendment to board's constitution
First Cricket News

Sourav Ganguly all set to continue as BCCI president for another term after SC accepts amendment to board's constitution

Supreme court do away with the three-year cooling-off period; allowing Sourav Ganguly and Jay Shah a shot at six-year tenure (two terms of three years each) at a stretch as BCCI president and secretary respectively

Hijab row: Karnataka AG says hijab in classes not akin to transgender rights to dress as expression
India

Hijab row: Karnataka AG says hijab in classes not akin to transgender rights to dress as expression

The apex court is hearing arguments on a batch of petitions challenging the Karnataka High Court verdict refusing to lift the ban on hijab in educational institutions of the state that have prescribed uniforms

Hijab row not spontaneous, part of larger conspiracy by PFI in 2022: SG Tushar Mehta
India

Hijab row not spontaneous, part of larger conspiracy by PFI in 2022: SG Tushar Mehta

The apex court is hearing arguments on a batch of petitions challenging the Karnataka High Court verdict refusing to lift the ban on hijab in educational institutions of the state that have prescribed uniforms