Kudankulam nuclear plant to begin commercial operations next month

The Nuclear Power Corporation of India Ltd (NPCIL) is expected to start commercial operations of its first 1,000 MW unit at Kudankulam Nuclear Power Project (KNPP) next month, said a senior official Thursday.

hidden August 28, 2014 15:41:55 IST
Kudankulam nuclear plant to begin commercial operations next month

Chennai: The Nuclear Power Corporation of India Ltd (NPCIL) is expected to start commercial operations of its first 1,000 MW unit at Kudankulam Nuclear Power Project (KNPP) next month, said a senior official Thursday.

"We have to get the AERB's (Atomic Energy Regulatory Board) permission to restart the unit. The meeting with AERB is slated 30 August," the official told IANS preferring anonymity.

Kudankulam nuclear plant to begin commercial operations next month

Representational image. PTI

He said the unit, after restarting, would take around one week to reach its full power levels.

He said all the mandatory tests have been completed and the reports have been submitted to AERB.

India's atomic power plant operator NPCIL is setting up two 1,000 MW Russian reactors at Kudankulam in Tirunelveli district, 650 km from here. The total outlay for the project is over Rs.17,000 crore.

The KNPP is India's first pressurised water reactor belonging to the light water reactor category.

The first unit attained criticality July 2013, which is the beginning of the fission process.

Normally, the NPCIL announces the date of the postponement of commercial operations around 15th of every month. But till this time, no such announcement has been made giving a hope that the first unit would start commercial operations in August.

As of July 2014, the physical progress of the unit stands at 99.95 percent.

During the trial run, though the KNPP fed the southern grid with power, it is considered as infirm power and NPCIL will not get the full revenue.

Queried about the status of the second unit, the official said AERB's permission is awaited to carry out the hot run or operating the nuclear steam supply systems with the dummy fuel.

The dummy fuel assemblies, made of lead instead of uranium are the exact replica of the actual nuclear fuel assemblies, both in dimension and weight.

During the hot run process, the nominal parameters of the plant are achieved and tests are conducted for design evaluation of the plant. After this, the nuclear fuel is loaded and the reactor is made critical - the time when the fission process start.

The second 1,000 MW is expected to start commercial operations in March 2015 on a date which is under review.

The physical progress of the unit stands at 97.44 percent as on July 2014.

IANS

Updated Date:

Find latest and upcoming tech gadgets online on Tech2 Gadgets. Get technology news, gadgets reviews & ratings. Popular gadgets including laptop, tablet and mobile specifications, features, prices, comparison.

also read

Kudankulam-I to begin power production within this month: Govt
India

Kudankulam-I to begin power production within this month: Govt

Kudankulam Nuclear Power Project (KNPP) in Tamil Nadu, which has been hit by protests, will start power production within this month, Union Minister V Narayanasamy said on Wednesday.

Commercial operation of Kudankulam plant may begin next month
India

Commercial operation of Kudankulam plant may begin next month

The commercial operation of the 1000 MW first unit of the Indo-Russian project was slated for commissioning this month but is now expected in March, Nuclear Power Corporation of India Limited (NPCIL) said.

Kudankulam Nuclear Power Plant construction begins, expected to finish in 73 months
India

Kudankulam Nuclear Power Plant construction begins, expected to finish in 73 months

The NPCIL on Thursday put the 'first pour of concrete' for unit three of Kudankulam Nuclear Power Plant (KKNPP), marking the commencement of construction work with a deadline.