Three expressways/green corridors to be completed in 3 years; 22 to be built at Rs 3 lakh cr: Nitin Gadkari
The government plans to complete three of the 22 expressways and green corridors in the next three years, including the flagship Delhi Mumbai Expressway being built at a new alignment, Union minister Nitin Gadkari has said

-
22 projects comprising 7,500 km of greenfield expressways and corridors are planned to be completed by FY25 at a cost of Rs 3.10 lakh crore, Gadkari said
-
Of the projects, six are 2,250 km expressways to be built at a cost of Rs 1.45 lakh crore
-
The remaining 16 are greenfield corridors, including 5,250 km projects to be constructed at a cost of Rs 1.65 lakh crore
New Delhi: The government plans to complete three of the 22 expressways and green corridors in the next three years, including the flagship Delhi Mumbai Expressway being built at a new alignment, Union minister Nitin Gadkari has said.
These 22 projects comprising 7,500 km of greenfield expressways and corridors are planned to be completed by FY25 at a cost of Rs 3.10 lakh crore.
"We will complete the flagship Delhi Mumbai Express Highway in the next three years. The work will be done in 51 packages and work has already been started on 18. This will be India's longest expressway at 1,320 km and will reduce travel time between Delhi and Mumbai from 24 hours to 13 hours," the road transport and highways minister said.
Of the projects, six are 2,250 km expressways to be built at a cost of Rs 1.45 lakh crore.

File image of union road transport minister Nitin Gadkari. PTI
The remaining 16 are greenfield corridors, including 5,250 km projects to be constructed at a cost of Rs 1.65 lakh crore
Besides Delhi Mumbai Expressway, the minister said the trans-Rajasthan and trans-Haryana projects will be completed within the next three years.
About Delhi Mumbai Expressway, he said greenfield alignment has been selected to avoid habitation and optimise the cost of land acquisition.
"We have saved about Rs 16,000 crore on land acquisition front alone as land could be acquired at a cost of Rs 80 lakh per hectare for the project," he said, adding that the expressway will unlock new economic opportunities in hinterland districts of Haryana, Rajasthan, Madhya Pradesh and Gujarat.
The expressway has been taken from concept to award in a record time-frame of less than a year.
He said the new projects will provide alternate routes to diversify traffic, improve geometry/alignment and provide connectivity for major towns, thereby reducing distance and travel times
Besides, these will mitigate issues like land acquisition, utility shifting and other clearances related to the brown-field expansion of existing alignment and provide thrust to the economy of backward regions by improving infrastructure, the minister said.
Subscribe to Moneycontrol Pro at ₹499 for the first year. Use code PRO499. Limited period offer. *T&C apply
also read

Suspected Russian hack in Texas-based SolarWinds fuels new US action on cybersecurity
The hackers had unfettered access to the data and email of at least nine US government agencies and about 100 private companies, with the full extent of the compromise still unknown

Front passenger airbag mandatory for all cars sold in India starting 31 August, 2021
All new vehicles that go on sale in India will need to have dual front airbags starting 1 April, 2021, while the deadline for existing models is 31 August.

Renewal of driving licence, learner’s licence application among 18 new RTO services available online
18 new services can be completed online with Aadhar-based authentication and no longer warrant a visit to the local RTO.