Reliance says its main gas fields in KG-D6 block in late-life stage, output plummets to all-time low

KG-D6 had hit a peak of 69.43 mmscmd in March 2010 before water and sand ingress shut down wells

Press Trust of India July 22, 2019 09:52:40 IST
Reliance says its main gas fields in KG-D6 block in late-life stage, output plummets to all-time low
  • Beginning mid-2020, Reliance Industries will bring to production three sets of new discoveries in the block

  • RIL has till date made 19 oil and gas discoveries in the Krishna Godavari basin

  • KG-D6 had hit a peak of 69.43 mmscmd in March 2010 before water and sand ingress shut down wells

New Delhi: Reliance Industries has said its flagship natural gas fields in the KG-D6 block in the Bay of Bengal are in "a late-life stage" with output plummeting to an all-time low.

The company, beginning mid-2020, will bring to production three sets of new discoveries in the block that will reverse the years of decline in production.

Dhirubhai-1 and 3—once the country's highest gas producing fields—are "in a late-stage and affected by low pressure and water ingress related challenges," the company said in an investor presentation post announcing June quarter earnings.

The fields produced an average of 1.76 million standard cubic metres per day of gas during April-June, the firm said.

RIL has till date made 19 oil and gas discoveries in the Krishna Godavari basin. Of these, MA—the only oil discovery in the block—began production in September 2008. D1 and D3 fields went onstream in April 2009.

MA field ceased to produce in September last year and now D1 and D3 are in their last stage.

Reliance says its main gas fields in KGD6 block in latelife stage output plummets to alltime low

RIL KG-D6 field. Reuters

KG-D6 had hit a peak of 69.43 mmscmd in March 2010 before water and sand ingress shut down wells. This peak output comprised 66.35 mmscmd from D1 and D3, the largest of the gas discoveries on the KG-D6 block, and 3.07 mmscmd from MA field.

Gas production from MA field hit a peak of 6.78 mmscmd in January 2012.

RIL in the presentation said it is now developing three sets of discoveries—R-Cluster, Satellite Cluster and MJ fields in KG-D6 block and these will together produce 30-35 mmscmd of peak output.

"R-Cluster development (is) on track for first gas in mid-2020," it said. "Satellite Cluster on track for first gas in Mid-2021 (and) MJ Development on track for production in Mid-2022."

While all six wells on R-Cluster have been completed and now the second phase of offshore installation activities are planned on the field in Q3 of FY20, for Satellite fields and MJ field all contracts have been awarded, it said.

RIL is the operator of the block with 60 percent interest while BP holds 30 percent stake. Niko Resources of Canada has the remaining 10 percent but it has defaulted on payments, triggering the process of assignment of its interest to RIL and BP.

"Assignment of Niko's PI (participating interest) to RIL and BP is in progress," the company said in the presentation.

MJ gas find is located about 2,000 metres directly below the currently producing D1 and D3 fields and is estimated to hold a minimum of 0.988 Trillion cubic feet (Tcf) of contingent resource.

Besides MJ-1, four deepsea satellite gas discoveries—D-2, 6, 19 and 22—are planned to be developed together with D29 and D30 finds on the block. The third set is the D-34 or R-Series find.

Other discoveries have either been surrendered or taken away by the government for not meeting timelines for beginning production.

Disclaimer: Reliance Industries Ltd. is the sole beneficiary of Independent Media Trust which controls Network18 Media & Investments Ltd.

Updated Date:

also read

RIL-BP get nod to invest $3.18 bn in R-Series gas field
Business

RIL-BP get nod to invest $3.18 bn in R-Series gas field

Reliance Industries and its partner BP Plc today won approval to invest $3.18 billion in the R-Series gas field in the flagging KG-D6 block.

Reliance Industries, BP to invest $1.5 bn to develop satellite gas fields in KG-D6 block by 2022
Business

Reliance Industries, BP to invest $1.5 bn to develop satellite gas fields in KG-D6 block by 2022

The government had in 2012 approved a $1.529 billion plan to produce 10.36 million standard cubic meters per day of gas from four satellite fields of block KG-DWN-98/3 (KG—D6) by 2016-17.

Rajya Sabha bids farewell to 54 retiring members
India

Rajya Sabha bids farewell to 54 retiring members

Chidambaram said the government will not go back on its decision to raise gas prices for both public sector and private producers from 1 April.