Firstpost
  • Home
  • Video Shows
    Vantage Firstpost America Firstpost Africa First Sports
  • World
    US News
  • Explainers
  • News
    India Opinion Cricket Tech Entertainment Sports Health Photostories
  • Asia Cup 2025
Apple Incorporated Modi ji Justin Trudeau Trending

Sections

  • Home
  • Live TV
  • Videos
  • Shows
  • World
  • India
  • Explainers
  • Opinion
  • Sports
  • Cricket
  • Health
  • Tech/Auto
  • Entertainment
  • Web Stories
  • Business
  • Impact Shorts

Shows

  • Vantage
  • Firstpost America
  • Firstpost Africa
  • First Sports
  • Fast and Factual
  • Between The Lines
  • Flashback
  • Live TV

Events

  • Raisina Dialogue
  • Independence Day
  • Champions Trophy
  • Delhi Elections 2025
  • Budget 2025
  • US Elections 2024
  • Firstpost Defence Summit
Trending:
  • Charlie Kirk shot dead
  • Nepal protests
  • Russia-Poland tension
  • Israeli strikes in Qatar
  • Larry Ellison
  • Apple event
  • Sunjay Kapur inheritance row
fp-logo
Infra projects' cost overrun crosses Rs 4 lakh-cr mark over delays in land acquisition, forest clearance: Report
Whatsapp Facebook Twitter
Whatsapp Facebook Twitter
Apple Incorporated Modi ji Justin Trudeau Trending

Sections

  • Home
  • Live TV
  • Videos
  • Shows
  • World
  • India
  • Explainers
  • Opinion
  • Sports
  • Cricket
  • Health
  • Tech/Auto
  • Entertainment
  • Web Stories
  • Business
  • Impact Shorts

Shows

  • Vantage
  • Firstpost America
  • Firstpost Africa
  • First Sports
  • Fast and Factual
  • Between The Lines
  • Flashback
  • Live TV

Events

  • Raisina Dialogue
  • Independence Day
  • Champions Trophy
  • Delhi Elections 2025
  • Budget 2025
  • US Elections 2024
  • Firstpost Defence Summit
  • Home
  • Business
  • Infra projects' cost overrun crosses Rs 4 lakh-cr mark over delays in land acquisition, forest clearance: Report

Infra projects' cost overrun crosses Rs 4 lakh-cr mark over delays in land acquisition, forest clearance: Report

Press Trust of India • January 1, 2020, 16:27:32 IST
Whatsapp Facebook Twitter

As many as 388 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns of more than Rs 4 lakh crore owing to delays and other reasons, according to a report

Advertisement
Subscribe Join Us
Add as a preferred source on Google
Prefer
Firstpost
On
Google
Infra projects' cost overrun crosses Rs 4 lakh-cr mark over delays in land acquisition, forest clearance: Report

New Delhi: As many as 388 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns of more than Rs 4 lakh crore owing to delays and other reasons, according to a report. The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of such 1,636 projects, 388 projects reported cost overruns and 563 projects time escalation. “Total original cost of implementation of the 1,636 projects was Rs 19,52,524.85 crore and their anticipated completion cost is likely to be Rs 23,53,108.80 crore, which reflects overall cost overruns of 4,00,583.95 crore (20.52 percent of original cost),” the ministry’s latest report for October 2019 said. [caption id=“attachment_4371135” align=“alignleft” width=“380”]Representational image. Reuters. Representational image. Reuters.[/caption] According to the report, the expenditure incurred on these projects till October 2019 is Rs 10.32 lakh crore, which is 43.86 percent of the anticipated cost of the projects. However, it said the number of delayed projects decreases to 490 if delay is calculated on the basis of the latest schedule of completion. Further, it said that for 720 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of the 563 delayed projects, 185 projects have overall delay in the range of 1 to 12 months, 123 projects in the range of 13 to 24 months, 136 projects reflect delay in the range of 25 to 60 months and 119 projects show delay of 61 months and above. The average time overrun in these 563 delayed projects is 38.74 months. The brief reasons for time overruns, as reported by various project implementing agencies, are delays in land acquisition, forest clearance and supply of equipment. Besides, there are other reasons like fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, Maoist problems, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation, among others, the report said. It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, indicating that time or cost overrun figures are under-reported.

Tags
NewsTracker Infrastructure Land acquisition Infrastructure Projects Forest clearance Ministry of Statistics and Programme Implementation
End of Article
Latest News
Find us on YouTube
Subscribe
End of Article

Impact Shorts

Chennai Ranks #1 in Challan Checks: ACKO Insights for Smarter Car and Two Wheeler Insurance Decisions

Chennai Ranks #1 in Challan Checks: ACKO Insights for Smarter Car and Two Wheeler Insurance Decisions

Chennai leads India in challan checks, with drivers checking their e-challans over 5 times a month on average. Helmet non-compliance is the most broken rule, accounting for 34.8% of all traffic offences in Chennai. Regular digital challan checks help drivers avoid hefty fines, promote safe driving, and improve insurance premiums.

More Impact Shorts

Top Stories

Charlie Kirk, shot dead in Utah, once said gun deaths are 'worth it' to save Second Amendment

Charlie Kirk, shot dead in Utah, once said gun deaths are 'worth it' to save Second Amendment

From governance to tourism, how Gen-Z protests have damaged Nepal

From governance to tourism, how Gen-Z protests have damaged Nepal

Did Russia deliberately send drones into Poland’s airspace?

Did Russia deliberately send drones into Poland’s airspace?

Netanyahu ‘killed any hope’ for Israeli hostages: Qatar PM after Doha strike

Netanyahu ‘killed any hope’ for Israeli hostages: Qatar PM after Doha strike

Charlie Kirk, shot dead in Utah, once said gun deaths are 'worth it' to save Second Amendment

Charlie Kirk, shot dead in Utah, once said gun deaths are 'worth it' to save Second Amendment

From governance to tourism, how Gen-Z protests have damaged Nepal

From governance to tourism, how Gen-Z protests have damaged Nepal

Did Russia deliberately send drones into Poland’s airspace?

Did Russia deliberately send drones into Poland’s airspace?

Netanyahu ‘killed any hope’ for Israeli hostages: Qatar PM after Doha strike

Netanyahu ‘killed any hope’ for Israeli hostages: Qatar PM after Doha strike

Top Shows

Vantage Firstpost America Firstpost Africa First Sports
Latest News About Firstpost
Most Searched Categories
  • Web Stories
  • World
  • India
  • Explainers
  • Opinion
  • Sports
  • Cricket
  • Tech/Auto
  • Entertainment
  • IPL 2025
NETWORK18 SITES
  • News18
  • Money Control
  • CNBC TV18
  • Forbes India
  • Advertise with us
  • Sitemap
Firstpost Logo

is on YouTube

Subscribe Now

Copyright @ 2024. Firstpost - All Rights Reserved

About Us Contact Us Privacy Policy Cookie Policy Terms Of Use
Home Video Shorts Live TV