Firstpost
  • Home
  • Video Shows
    Vantage Firstpost America Firstpost Africa First Sports
  • World
    US News
  • Explainers
  • News
    India Opinion Cricket Tech Entertainment Sports Health Photostories
  • Asia Cup 2025
Apple Incorporated Modi ji Justin Trudeau Trending

Sections

  • Home
  • Live TV
  • Videos
  • Shows
  • World
  • India
  • Explainers
  • Opinion
  • Sports
  • Cricket
  • Health
  • Tech/Auto
  • Entertainment
  • Web Stories
  • Business
  • Impact Shorts

Shows

  • Vantage
  • Firstpost America
  • Firstpost Africa
  • First Sports
  • Fast and Factual
  • Between The Lines
  • Flashback
  • Live TV

Events

  • Raisina Dialogue
  • Independence Day
  • Champions Trophy
  • Delhi Elections 2025
  • Budget 2025
  • US Elections 2024
  • Firstpost Defence Summit
Trending:
  • PM Modi in Manipur
  • Charlie Kirk killer
  • Sushila Karki
  • IND vs PAK
  • India-US ties
  • New human organ
  • Downton Abbey: The Grand Finale Movie Review
fp-logo
Oil Min delays in KG gas project approvals cost firm 3 years: ONGC
Whatsapp Facebook Twitter
Whatsapp Facebook Twitter
Apple Incorporated Modi ji Justin Trudeau Trending

Sections

  • Home
  • Live TV
  • Videos
  • Shows
  • World
  • India
  • Explainers
  • Opinion
  • Sports
  • Cricket
  • Health
  • Tech/Auto
  • Entertainment
  • Web Stories
  • Business
  • Impact Shorts

Shows

  • Vantage
  • Firstpost America
  • Firstpost Africa
  • First Sports
  • Fast and Factual
  • Between The Lines
  • Flashback
  • Live TV

Events

  • Raisina Dialogue
  • Independence Day
  • Champions Trophy
  • Delhi Elections 2025
  • Budget 2025
  • US Elections 2024
  • Firstpost Defence Summit
  • Home
  • Business
  • Corporate
  • Oil Min delays in KG gas project approvals cost firm 3 years: ONGC

Oil Min delays in KG gas project approvals cost firm 3 years: ONGC

FP Archives • September 1, 2014, 16:37:37 IST
Whatsapp Facebook Twitter

ONGC says it lost three years because the ministry and DGH refused to approve its partnership with Norway’s Statoil and Petrobras of Brazil for the block.

Advertisement
Subscribe Join Us
Add as a preferred source on Google
Prefer
Firstpost
On
Google
Oil Min delays in KG gas project approvals cost firm 3 years: ONGC

New Delhi: As Oil Ministry looks into reasons for delay in ONGC’s KG basin gas development, the state-owned firm says it lost three years because the ministry and DGH refused to approve its partnership with Norway’s Statoil and Petrobras of Brazil for the block.

Oil and Natural Gas Corp (ONGC) had in 2007 farmed out 15 percent stake in the KG-DWN-98/2 block, which sits next to Reliance Industries’ KG-D6 block, to Brazil’s state-controlled oil firm Petroleo Brasileiro SA or Petrobras. Another 10 percent interest was given to Norway’s Norsk Hydro (now Statoil Hydro).

STORY CONTINUES BELOW THIS AD

The two firm, who are among the biggest deepsea developers in the world, were to bring in technology and expertise to development of gas discoveries in KG-DWN-98/2 or KG-D5 block of ONGC.

More from Corporate
Maha: Court orders Rs 30L compensation for parents after youth dies in road accident Maha: Court orders Rs 30L compensation for parents after youth dies in road accident Ashleigh Barty comes from set down to beat Coco Gauff in Australian Open lead-up Ashleigh Barty comes from set down to beat Coco Gauff in Australian Open lead-up

[caption id=“attachment_87920” align=“alignleft” width=“380”] ![Image taken from website](https://images.firstpost.com/wp-content/uploads/2014/06/ONGClogoWebsite.jpg) Image taken from website[/caption]

However, the ministry and its technical arm Directorate General of Hydrocarbons (DGH) did not approve the equity participation of the foreign companies, leading to inordinate delays in clearing of drilling programme, ONGC sources said.

Frustrated at delays, the two firms finally walked out of the block in 2010.

KG-D5 block was originally planned to start producing gas from 2014 with a peak of about 20-25 million standard cubic meters per day. Now, the block will not produce before 2018.

After the pullout of Petrobras and Statoil, ONGC, which does not have the technology to produce gas from deepsea in geologically hostile KG basin, tried to rope in other foreign energy majors but its attempts were frustrated as it could not get approvals, sources said.

After the new government took over, the Oil Ministry is looking into reasons why ONGC has not started natural gas production from KG-D5, where 11 oil and gas discoveries have been made so far. In contrast, RIL’s neighbouring KG-D6 block started gas output in April 2009.

STORY CONTINUES BELOW THIS AD

Shortly after the pullout by Petrobras and Statoil in 2010, the then ONGC Chairman R S Sharma had shot off an angry letter to the oil secretary saying red tape was making international oil majors apprehensive over sharing exploration risks in acreages where they pick up stake.

“This was done by ONGC as a part of its strategy to capitalise on the technological experience of international companies of repute in the development of deepwater discoveries,” Sharma wrote.

He stated that although the farm out agreements with Petrobras and Statoil were signed in August/September, 2007, “Joint Operating Agreement (JOA) could not be signed with both these companies, initially, due to 9 months taken in obtaining approval on assignment of participating interest, and then one year in signing amendment to the Production Sharing Contract (PSC) from various parties, including government.”

ONGC has made 11 oil and gas discoveries in the Block KG-DWN-98/2 or KG-D5. The block is divided into a Northern Discovery Area (NDA) and Southern Discovery Area (SDA).

STORY CONTINUES BELOW THIS AD

It plans to invest $9 billion in producing from discoveries in NDA, sources said.

ONGC is looking at producing 2.5-3 million tonnes of oil per annum and 9-10 million standard cubic metres per day of gas from the Northern Development Area of KG-D5 block.

NDA holds an estimated 92.30 million tonnes of oil reserves and 97.568 billion cubic metres of inplace gas reserves spread over seven fields.

Sources said ONGC has submitted to the DGH a Declaration of Commerciality (DoC) for the oil find in the NDA and a detailed field development plan will be submitted by year-end.

ONGC bought 90 percent interest in Block KG-D5 from Cairn Energy India Ltd in 2005. Cairn still holds 10 percent in the block. Before selling most of its stake and giving away operatorship of the block, Cairn made four discoveries in the area - Padmavati, Kanakdurga, N-1 and R-1 (Annapurna).

Subsequently, ONGC made six significant discoveries - E-1, A1, U1, W1, D-1 and KT-1 in NDA and the first ultra-deepwater discovery UD-1 at a record depth of 2,841 metres.

STORY CONTINUES BELOW THIS AD

The NDA comprises discoveries like Padmawati, Kanadurga, D, E, U, A, while the ultra deepsea UD find lies in SDA. ONGC, sources said, is looking at producing oil and gas from NDA using a floating production, storage and offloading (FPSO) unit.

An investment plan for UD-1 will be submitted separately, they added.

PTI

Tags
India oil Oil Ministry ONGC RIL Petrobas KG Statoil
End of Article
Written by FP Archives

see more

Latest News
Find us on YouTube
Subscribe
End of Article

Top Stories

Russian drones over Poland: Trump’s tepid reaction a wake-up call for Nato?

Russian drones over Poland: Trump’s tepid reaction a wake-up call for Nato?

As Russia pushes east, Ukraine faces mounting pressure to defend its heartland

As Russia pushes east, Ukraine faces mounting pressure to defend its heartland

Why Mossad was not on board with Israel’s strike on Hamas in Qatar

Why Mossad was not on board with Israel’s strike on Hamas in Qatar

Turkey: Erdogan's police arrest opposition mayor Hasan Mutlu, dozens officials in corruption probe

Turkey: Erdogan's police arrest opposition mayor Hasan Mutlu, dozens officials in corruption probe

Russian drones over Poland: Trump’s tepid reaction a wake-up call for Nato?

Russian drones over Poland: Trump’s tepid reaction a wake-up call for Nato?

As Russia pushes east, Ukraine faces mounting pressure to defend its heartland

As Russia pushes east, Ukraine faces mounting pressure to defend its heartland

Why Mossad was not on board with Israel’s strike on Hamas in Qatar

Why Mossad was not on board with Israel’s strike on Hamas in Qatar

Turkey: Erdogan's police arrest opposition mayor Hasan Mutlu, dozens officials in corruption probe

Turkey: Erdogan's police arrest opposition mayor Hasan Mutlu, dozens officials in corruption probe

Top Shows

Vantage Firstpost America Firstpost Africa First Sports
Latest News About Firstpost
Most Searched Categories
  • Web Stories
  • World
  • India
  • Explainers
  • Opinion
  • Sports
  • Cricket
  • Tech/Auto
  • Entertainment
  • IPL 2025
NETWORK18 SITES
  • News18
  • Money Control
  • CNBC TV18
  • Forbes India
  • Advertise with us
  • Sitemap
Firstpost Logo

is on YouTube

Subscribe Now

Copyright @ 2024. Firstpost - All Rights Reserved

About Us Contact Us Privacy Policy Cookie Policy Terms Of Use
Home Video Shorts Live TV