CERC admits two Reliance Power petitions for Sasan plant

Reliance Power through its subsidiary Sasan Power Ltd is setting up the 4,000 MW ultra mega power project at Sasan in Madhya Pradesh.<br /><br />

hidden April 16, 2013 18:10:11 IST
CERC admits two Reliance Power petitions for Sasan plant

New Delhi: Electricity sector regulator CERC today admitted two petitions filed by Reliance Power seeking compensation for the increased cost on setting up 4,000 MW Sasan project due to rise in construction cost and fall in rupee value.

The Central Electricity Regulatory Commission (CERC) has admitted both the petitions, said Amit Kapur, counsel for Reliance Power.

In one of the petitions, the company has sought compensation considering a change in law during the construction period. In the second petition, it has asked for a compensation on account of unforeseen depreciation in rupee.

CERC admits two Reliance Power petitions for Sasan plant

Power woes. Reuters

Reliance Power through its subsidiary Sasan Power Ltd is setting up the 4,000 MW ultra mega power project at Sasan in Madhya Pradesh.

The company bagged this project in 2007 in a global tender quoting the lowest 'levelised' tariff of Rs 1.19 per unit for 25 years.

As per the Power Purchase Agreement (PPA) between the developer of the project and procurer of electricity, the company can approach CERC for any Change in Law during the construction period and fluctuation in the value of the rupee.

Power Finance Corporation, is the nodal agency for the UMPPs in the country, it has awarded four such projects of which Reliance Power have bagged three -- Krishnapatnam (Andhra Pradesh) and Tilaiya ( Jharkhand) apart from Sasan.

Tata Power has set up a 4,000 MW Mundra plant in Gujarat.

An UMPP is a power plant of at least 4,000 MW generation capacity.

In a significant ruling, the national electricity regulator on Monday had allowed Tata Power to raise power tariffs to compensate for an unexpected increase in coal cost.

The CERC asked states that buy electricity from Tata Power's 4,000 megawatt Mundra Plant in Gujarat to form an expert panel to decide on compensating the firm for higher cost of coal imports from Indonesia.

The ruling was similar to the regulator's 2 April order allowing Adani Power to charge more for electricity produced at its Mundra plant in Gujarat.

PTI

Updated Date:

Subscribe to Moneycontrol Pro at ₹499 for the first year. Use code PRO499. Limited period offer. *T&C apply

also read

RPower asks CAG to drop charges of 'undue benefit'
Business

RPower asks CAG to drop charges of 'undue benefit'

Reliance Power's request comes after the government recently gave it a clean chit over transferring surplus coal from Sasan project in Madhya Pradesh to another power plant.

RPower's Maha plant begins electricity generation
Business

RPower's Maha plant begins electricity generation

Power major Reliance Power said that its two units of its 600 MW Butibori thermal power plant in Maharashtra have started generating electricity. RPower has invested Rs 3,600 crore in the Butibori plant.

RPower commissions 45 MW wind project in Maharashtra
Fwire

RPower commissions 45 MW wind project in Maharashtra

The 45 MW wind project, set up with an investment of Rs 300 crore, consists of 18 wind turbine generators.